BAKU TBILISI CEYHAN RAW PETROLEUM PIPE LINE CEYHAN TERMINAL SEA and LAND WORK CONSTRUCTIONS

The R&D researches has been concluded in 6 stages by taking into consideration the requirements of the contract. There was a need for a vessel with a built-on transmixer and concrete pump to build the sea quay of the BTC Pipe Line construction. The rental fee of this vessel was around 3.5 million dollars. Instead of it, we have solved this problem, with some engineering calculations and using our existing equipment, the sea constructions' concrete was dumped without any problem and by spending only 150,000 dollars. This process created benefit to the country economy and also reduced the contractor's cost by many times.

 
1
/
20
   
LOCATION Botaž Facilities Ceyhan - Adana
CLASS OF CONCRETE C14-C40
AMOUNT OF CONCRETE 135.000 m3
STARTING AND FINISHING DATES 2004-2005
 
 